Start Date: 2/22/2024
| Progress Check | Expected Days Until Progress Check Remaining |
|---|---|
| Progress Check 1 - 3/12/2024 | Overdue by 634 days |
| Progress Check 2 - 4/7/2024 | Progress Check Passed |
| Progress Check 3 - 5/3/2024 | Overdue by 582 days |
| Progress Check 4 - 5/22/2024 | Overdue by 563 days |
Total Reservations: 29
Total Cancellations: 9
| Date | Title | Comment |
|---|---|---|
| 2/28/2024 | Weather - excessive crosswinds | No comment provided |
| 2/29/2024 | Weather - excessive crosswinds | No comment provided |
| 2/29/2024 | Weather - low cloud layers/ceilings | No comment provided |
| 3/15/2024 | Reschedule - booking is not needed | No comment provided |
| 3/18/2024 | Client - personal scheduling conflict | out of town |
| 3/20/2024 | Reschedule - client is scheduled for progress check | No comment provided |
| 3/21/2024 | Reschedule - client is scheduled for progress check | No comment provided |
| 3/30/2024 | Reschedule - changing booking | the race will be interfering during taxi |
| 4/1/2024 | Client - client discontinued training | Had to leave early to avoid weather on return drive to northeast. |
The percentage of the time that a lesson is marked as satisfactory. This does not include cancellations.
| Total Reservations | Total Passes | Total Times Marked "Repition Needed" |
|---|---|---|
| 20 | 5 | 15 |